π Interconnection Weekly: Project Updates You Need to Know (4/21/2025 - 5/4/2025)
122 projects moved in the interconnection queues across the country in the past week
Special Note: Looking to buy or sell a project in the interconnection queue? Weβre actively connecting developers with vetted, transaction-ready buyers and sellers at key decision points. Fill out this short form to get matched with serious players already in the market.
We saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
Round Valley β Peacock 230 kV line, Mead Switchyard 230 kV β 312MW battery + wind ππ¨ project in Yavapai, AZ (WAPA Desert Southwest Region). Proposed completion changed from November 30, 2028 to March 31, 2028
Keota 345kV Substation β 299MW battery + solar πβοΈ project in Weld County, CO (Tri-State Generation and Transmission Association). Proposed completion changed from May 31, 2026 to March 31, 2030
Henry Lake -Story 230kV Line β 299MW battery + solar πβοΈ project in Weld County, CO (Tri-State Generation and Transmission Association). Proposed completion changed from December 30, 2025 to February 26, 2029
Huckleberry 230kV Substation β 299MW battery + solar πβοΈ project in Pueblo County, CO (Tri-State Generation and Transmission Association). Proposed completion changed from November 30, 2026 to March 30, 2028
Keota 345kV Substation β 299MW battery + solar πβοΈ project in Weld County, CO (Tri-State Generation and Transmission Association). IA date changed from May 31, 2026 to March 31, 2030
Henry Lake -Story 230kV Line β 299MW battery + solar πβοΈ project in Weld County, CO (Tri-State Generation and Transmission Association). IA date changed from December 30, 2025 to February 26, 2029
Huckleberry 230kV Substation β 299MW battery + solar πβοΈ project in Pueblo County, CO (Tri-State Generation and Transmission Association). IA date added March 30, 2028
South Fork 115kV Substation β 237MW battery + solar πβοΈ project in Kit Carson County, CO (Tri-State Generation and Transmission Association). Proposed completion changed from December 30, 2025 to June 28, 2027
South Fork 115kV Substation β 237MW battery + solar πβοΈ project in Kit Carson County, CO (Tri-State Generation and Transmission Association). IA date changed from December 30, 2025 to June 28, 2027
Maid 161kV substation β 100MW battery π project in Mayes County, OK (SPP). Proposed completion changed from May 31, 2025 to November 29, 2027
Hell Creek Substation β 90MW battery + solar πβοΈ project in Kit Carson County, CO (Tri-State Generation and Transmission Association). Proposed completion changed from May 31, 2025 to September 30, 2028
Hell Creek Substation β 90MW battery + solar πβοΈ project in Kit Carson County, CO (Tri-State Generation and Transmission Association). IA date changed from May 31, 2025 to September 30, 2028
Neset 230kV Substation β 74MW battery π project in Montrail County, ND (SPP). Proposed completion changed from December 30, 2026 to December 30, 2027
Dulles Solar and BESS β 50MW battery π project in Loudoun County, VA (PJM). Proposed completion changed from October 30, 2026 to October 30, 2027
Distribution Feeder β 1MW hydro π§ project in Twin Falls, ID (Idaho Power Company). IA date added April 21, 2025
Custer/McNeil Substations, New Substation Near Hilltop/Stadium Substations β project in Pierce County, WA (Tacoma Public Utilities). Proposed completion changed from April 30, 2026 to December 8, 2026
TEXPO β 680MW gas π₯ project in Wilbarger, TX (ERCOT). Proposed completion changed from October 30, 2026 to October 30, 2027
Hiru Solar β 603MW solar βοΈ project in Clay, TX (ERCOT). Proposed completion changed from May 28, 2026 to March 31, 2029
Hiru Storage β 503MW battery π project in Clay, TX (ERCOT). Proposed completion changed from March 30, 2028 to March 31, 2029
Millsing BESS β 501MW battery π project in Grimes, TX (ERCOT). Proposed completion changed from June 30, 2027 to October 14, 2028
Scorpius Solar β 500MW solar βοΈ project in Milam, TX (ERCOT). Proposed completion changed from October 22, 2026 to November 15, 2028
Hollow Branch Creek Solar β 460MW solar βοΈ project in Leon, TX (ERCOT). IA date added October 21, 2024
TRIFECTA Gas β 453MW gas π₯ project in Midland, TX (ERCOT). Proposed completion changed from December 30, 2027 to October 30, 2029
Cold Creek Solar 2 β 445MW solar βοΈ project in Schleicher, TX (ERCOT). IA date added April 22, 2025
Western Flats Solar β 410MW solar βοΈ project in Crane, TX (ERCOT). Proposed completion changed from December 30, 2026 to October 31, 2028
Caliche Mound Solar β 408MW solar βοΈ project in Deaf Smith, TX (ERCOT). Proposed completion changed from August 27, 2025 to October 9, 2026
SOUTHERN SELECT ENERGY STORAGE β 404MW battery π project in Galveston, TX (ERCOT). Proposed completion changed from January 31, 2026 to January 14, 2027
Chickahominy Solar 1 and 2 β 320MW solar βοΈ project in Charles City County, VA (PJM). Proposed completion changed from December 30, 2024 to December 30, 2025
Elio BESS β 317MW battery π project in Brazoria, TX (ERCOT). Proposed completion changed from December 1, 2026 to August 4, 2027
Red Egret BESS β 310MW battery π project in Galveston, TX (ERCOT). Proposed completion changed from December 30, 2025 to August 30, 2026
Cuchillas BESS β 306MW battery π project in Webb, TX (ERCOT). Proposed completion changed from August 31, 2027 to December 26, 2026
Grapefruit Solar β 301MW solar βοΈ project in Hidalgo, TX (ERCOT). IA date added April 9, 2025
Acker BESS β 301MW battery π project in Castro, TX (ERCOT). IA date added April 20, 2025
NIGHTHAWK STORAGE β 300MW battery π project in San Diego, CA (CAISO). Proposed completion changed from March 30, 2025 to September 30, 2025
ORIENT - NORTHBORO 345.0kV β 263MW gas π₯ project in Adair County, IA (MISO). Proposed completion changed from August 31, 2029 to August 31, 2027
Yellow Cat Wind β 262MW wind π¨ project in Navarro, TX (ERCOT). Proposed completion changed from September 29, 2026 to March 31, 2027
Miranda Solar Project β 261MW solar βοΈ project in Mcmullen, TX (ERCOT). Proposed completion changed from August 29, 2026 to December 5, 2027
Taormina Storage β 231MW battery π project in Bexar, TX (ERCOT). IA date added April 13, 2025
Dunkel BESS β 226MW battery π project in Lubbock, TX (ERCOT). Proposed completion changed from April 2, 2026 to November 1, 2027
Anila BESS β 209MW battery π project in Wilson, TX (ERCOT). Proposed completion changed from July 1, 2026 to June 29, 2028
ALWEST BESS β 208MW battery π project in Anderson, TX (ERCOT). Proposed completion changed from May 3, 2026 to April 18, 2028
Longfellow Solar II β 207MW solar βοΈ project in Pecos, TX (ERCOT). IA date added April 14, 2025
VERTUS ENERGY STORAGE β 207MW battery π project in Galveston, TX (ERCOT). IA date changed from March 26, 2024 to January 7, 2025
Hoyte Solar β 206MW solar βοΈ project in Milam, TX (ERCOT). Proposed completion changed from March 30, 2026 to December 14, 2026
Nockenut Springs Solar 3 β 203MW solar βοΈ project in Gonzales, TX (ERCOT). Proposed completion changed from May 4, 2027 to June 4, 2029
Nockenut Springs Solar 2 β 203MW solar βοΈ project in Guadalupe, TX (ERCOT). Proposed completion changed from May 4, 2027 to June 4, 2029
Nockenut Springs Solar 1 β 203MW solar βοΈ project in Guadalupe, TX (ERCOT). Proposed completion changed from May 4, 2027 to June 4, 2029
Loma Pinta Solar β 203MW solar βοΈ project in La Salle, TX (ERCOT). Proposed completion changed from May 30, 2026 to May 30, 2027
Staccato BESS β 202MW battery π project in Fayette, TX (ERCOT). Proposed completion changed from December 30, 2025 to December 30, 2026
Carolina Storage Odessa β 202MW battery π project in Howard, TX (ERCOT). Proposed completion changed from April 19, 2027 to July 31, 2028
Carolina Storage Wichita Falls β 202MW battery π project in Wichita, TX (ERCOT). Proposed completion changed from September 21, 2027 to July 31, 2028
Texas Cotton Solar β 201MW solar βοΈ project in Brazos, TX (ERCOT). Proposed completion changed from December 30, 2026 to December 30, 2028
Nockenut Springs Solar 4 β 201MW solar βοΈ project in Gonzales, TX (ERCOT). Proposed completion changed from May 4, 2027 to June 4, 2029
Echols Creek Solar β 201MW solar βοΈ project in Lamar, TX (ERCOT). Proposed completion changed from December 30, 2026 to October 12, 2027
Moonlight Sonata BESS β 201MW battery π project in Colorado, TX (ERCOT). Proposed completion changed from November 18, 2027 to June 30, 2028
Dios BESS β 201MW battery π project in Jackson, TX (ERCOT). IA date added April 2, 2025
Sengun BESS β 200MW battery π project in Nueces, TX (ERCOT). Proposed completion changed from January 5, 2026 to March 16, 2028
Kota Battery β 200MW battery π project in Carson, TX (ERCOT). Proposed completion changed from December 30, 2026 to October 30, 2028
Anila Solar β 200MW solar βοΈ project in Wilson, TX (ERCOT). Proposed completion changed from July 1, 2026 to June 29, 2028
Red Top Solar I β 200MW solar βοΈ project in Young, TX (ERCOT). Proposed completion changed from September 29, 2027 to April 12, 2028
Blackcat Storage β 200MW battery π project in Matagorda, TX (ERCOT). Proposed completion changed from April 5, 2026 to December 30, 2027
Iron Wolf Solar β 200MW solar βοΈ project in Van Zandt, TX (ERCOT). Proposed completion changed from December 30, 2026 to December 30, 2028
Accalia Point Solar β 190MW solar βοΈ project in Cameron, TX (ERCOT). Proposed completion changed from May 30, 2027 to November 30, 2028
Harryoung Solar β 190MW solar βοΈ project in Cameron, TX (ERCOT). Proposed completion changed from May 14, 2027 to May 14, 2028
HarryoungBESS β 190MW battery π project in Cameron, TX (ERCOT). Proposed completion changed from May 14, 2027 to May 14, 2028
Leighton Solar SLF β 183MW solar βοΈ project in Limestone, TX (ERCOT). Proposed completion changed from October 16, 2026 to April 29, 2027
Longfellow Solar I β 178MW solar βοΈ project in Pecos, TX (ERCOT). IA date added April 14, 2025
Sol Marina Energy Center β 175MW solar βοΈ project in Ellis, TX (ERCOT). IA date added April 24, 2025
Cold Creek Storage 2 β 174MW battery π project in Schleicher, TX (ERCOT). IA date added April 22, 2025
Flag City Storage SLF β 169MW battery π project in Jackson, TX (ERCOT). Proposed completion changed from December 30, 2026 to December 30, 2027
Flag City Solar β 167MW solar βοΈ project in Jackson, TX (ERCOT). Proposed completion changed from December 30, 2026 to December 30, 2027
Crowned Heron BESS 2 β 154MW battery π project in Fort Bend, TX (ERCOT). Proposed completion changed from July 30, 2025 to March 30, 2026
Quarter Ranch Solar β 154MW solar βοΈ project in Zapata, TX (ERCOT). Proposed completion changed from September 29, 2026 to October 14, 2028
Whiskey BESS β 153MW battery π project in Van Zandt, TX (ERCOT). Proposed completion changed from March 14, 2026 to January 29, 2027
Leon BESS β 153MW battery π project in Houston, TX (ERCOT). Proposed completion changed from February 15, 2028 to October 9, 2028
Zorro BESS β 153MW battery π project in Van Zandt, TX (ERCOT). Proposed completion changed from August 18, 2026 to April 30, 2027
El Patrimonio Solar β 152MW solar βοΈ project in Bexar, TX (ERCOT). Proposed completion changed from September 22, 2026 to April 28, 2027
Pink Solar β 151MW solar βοΈ project in Hunt, TX (ERCOT). IA date added August 29, 2022
Driet BESS β 150MW battery π project in Colorado, TX (ERCOT). Proposed completion changed from May 31, 2026 to October 14, 2027
Iron Wolf BESS β 150MW battery π project in Van Zandt, TX (ERCOT). Proposed completion changed from March 1, 2027 to December 30, 2028
Fluvanna Max Solar β 150MW solar βοΈ project in Scurry, TX (ERCOT). Proposed completion changed from September 27, 2028 to September 13, 2029
Riverstone Solar β 149MW solar βοΈ project in Buckingham County, VA (PJM). Proposed completion changed from August 29, 2026 to October 29, 2027
La Casa Wind β 148MW wind π¨ project in Stephens, TX (ERCOT). Proposed completion changed from June 29, 2025 to March 14, 2026
Rain Lily Solar 1 β 147MW solar βοΈ project in Hood, TX (ERCOT). Proposed completion changed from October 14, 2027 to October 14, 2028
Wensowitch Solar β 146MW solar βοΈ project in Navarro, TX (ERCOT). Proposed completion changed from September 22, 2027 to March 27, 2028
Brizo BESS β 140MW battery π project in Victoria, TX (ERCOT). IA date added March 26, 2025
Demeter Storage 2 β 138MW battery π project in Caldwell, TX (ERCOT). Proposed completion changed from December 30, 2026 to May 31, 2029
Giga Texas Data Center β 133MW battery π project in Travis, TX (ERCOT). IA date added April 29, 2025
Jumping Cactus Storage β 125MW battery π project in Duval, TX (ERCOT). Proposed completion changed from September 29, 2027 to October 14, 2028
Rock Island Generating (TEF -Due Diligence) β 121MW gas π₯ project in Colorado, TX (ERCOT). IA date added March 16, 2025
Dove Run Solar β 120MW solar βοΈ project in Duval, TX (ERCOT). Proposed completion changed from July 30, 2026 to October 14, 2027
Sun Cactus Solar β 120MW solar βοΈ project in Duval, TX (ERCOT). Proposed completion changed from August 30, 2026 to October 14, 2027
Longfellow BESS II β 105MW battery π project in Pecos, TX (ERCOT). IA date added April 14, 2025
Rain Lily Storage 1 β 105MW battery π project in Hood, TX (ERCOT). Proposed completion changed from October 14, 2027 to October 14, 2028
Carolina Storage Young County β 104MW battery π project in Young, TX (ERCOT). Proposed completion changed from September 21, 2027 to July 31, 2028
Pioneer Path Energy Storage 1 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Pioneer Path Energy Storage 2 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Pioneer Path Energy Storage 3 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Pioneer Path Energy Storage 4 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Prairie Horizon Energy Storage 1 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Prairie Horizon Energy Storage 2 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Prairie Horizon Energy Storage 3 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Prairie Horizon Energy Storage 4 β 103MW battery π project in Robertson, TX (ERCOT). Proposed completion changed from May 31, 2027 to November 30, 2027
Roost Energy Storage β 102MW battery π project in Scurry, TX (ERCOT). Proposed completion changed from September 14, 2026 to September 12, 2027
Holstein 2 Solar β 101MW solar βοΈ project in Nolan, TX (ERCOT). Proposed completion changed from April 30, 2027 to April 2, 2028
Paradiso BESS β 100MW battery π project in Atascosa, TX (ERCOT). IA date added April 17, 2025
Echols Creek Storage β 100MW battery π project in Lamar, TX (ERCOT). Proposed completion changed from December 30, 2026 to October 12, 2027
Demeter Solar β 88MW solar βοΈ project in Caldwell, TX (ERCOT). Proposed completion changed from March 27, 2026 to May 31, 2029
Hinkell BESS β 78MW battery π project in La Salle, TX (ERCOT). Proposed completion changed from April 30, 2026 to November 14, 2027
92kV P line β 70MW battery π project in Imperial County, CA (Imperial Irrigation District). Proposed completion changed from May 31, 2025 to May 31, 2028
Demeter Storage β 65MW battery π project in Caldwell, TX (ERCOT). Proposed completion changed from March 27, 2026 to May 31, 2029
Centennial Solar β 61MW solar βοΈ project in Menard, TX (ERCOT). Proposed completion changed from April 28, 2028 to April 29, 2029
Sol Marina Energy Center BESS β 57MW battery π project in Ellis, TX (ERCOT). IA date added April 24, 2025
Longfellow BESS I β 54MW battery π project in Pecos, TX (ERCOT). IA date added April 14, 2025
Bergen Generating Station β 51MW gas π₯ project in Bergen County, NJ (PJM). Proposed completion changed from May 30, 2026 to June 29, 2027
Voyager Storage β 50MW battery π project in Wharton, TX (ERCOT). Proposed completion changed from April 7, 2026 to April 7, 2028
Fluvanna Max BESS β 50MW battery π project in Scurry, TX (ERCOT). Proposed completion changed from September 27, 2028 to September 13, 2029
Redbud-Gaylord 34.5 kV β 30MW solar βοΈ project in Frederick County, VA (PJM). Proposed completion changed from March 30, 2025 to March 30, 2026
Shands Energy Center β 15MW battery π project in Sussex County, VA (PJM). Proposed completion changed from December 30, 2024 to December 30, 2025
Damon BESS 2 β 9MW battery π project in Brazoria, TX (ERCOT). Proposed completion changed from August 11, 2025 to August 20, 2026
Gears BESS β 9MW battery π project in Harris, TX (ERCOT). Proposed completion changed from February 14, 2025 to September 4, 2025
Roadrunner Crossing BESS SLF β battery π project in Eastland, TX (ERCOT). IA date added February 17, 2025