π Interconnection Weekly: Project Updates You Need to Know (6/15/2025 - 6/29/2025)
43 projects moved in the interconnection queues across the country in the past 2 weeks
Special Note: Interested in tracking project in the interconnection queues in real-time? Join the waiting list for early access to GridTracker here. Itβs the easiest way to get access to all of interconnection.fyiβs data.
We saw the following updates to U.S. transmission grid interconnection projects. For access to our live dataset, contact our sales team here.
ARIDA 2 SOLAR FARM β 700MW battery + solar πβοΈ project in Clark, NV (CAISO). Proposed completion changed from December 29, 2027 to May 30, 2029
Deedsville 345 kV Substation β 292MW solar βοΈ project in Miami County, IN (MISO). Proposed completion changed from July 31, 2023 to July 31, 2026
Substation 1363; 161kV Substation β 255MW gas π₯ project in Sarpy County, NE (SPP). Proposed completion changed from July 31, 2024 to June 16, 2025
Macomb to Ipava 138kV line β 200MW wind π¨ project in Mcdonough County, IL (MISO). Proposed completion changed from September 14, 2023 to September 14, 2026
Shockey 138kV β 200MW wind π¨ project in Logan County, IL (MISO). Proposed completion changed from October 30, 2023 to August 14, 2026
Ray Place Road - Washington #3 115 kV Line β 150MW solar βοΈ project in Taliaferro County, GA (Southern Company). Proposed completion changed from January 31, 2029 to January 16, 2028
Achord Road - Eastman Primary 230 kV Line β 150MW solar βοΈ project in Dodge County, GA (Southern Company). Proposed completion changed from August 14, 2028 to January 16, 2028
Hutsonville - Neoga 138 kV β 149MW solar βοΈ project in Cumberland County, IL (MISO). Proposed completion changed from July 31, 2023 to May 31, 2027
Bureau County 138 kV β 147MW wind π¨ project in Bureau County, IL (MISO). Proposed completion changed from July 31, 2022 to July 31, 2025
KENOWA - NELSON ROAD 345.0kV β 132MW solar βοΈ project in Montcalm County, MI (MISO). Proposed completion changed from October 31, 2023 to January 8, 2026
San Jose Rail Splitter 138KV (G515) β 100MW wind π¨ project in Tazewell County, IL (MISO). Proposed completion changed from August 31, 2024 to May 31, 2027
Eureka - Vestaburg 138kV Transmission Line (J1379 POI) β 100MW battery + solar πβοΈ project in Montcalm County, MI (MISO). Proposed completion changed from August 31, 2024 to June 6, 2027
Emery substation β 100MW battery π project in Emery, UT (PacifiCorp). Proposed completion changed from December 30, 2026 to June 29, 2027
ALTA VISTA SUNTOWER GENERATING STATION β 66MW battery + solar πβοΈ project in Los Angeles, CA (CAISO). Proposed completion changed from April 14, 2025 to December 10, 2027
Henry Solar β 20MW solar βοΈ project in Crawford County, PA (PJM). Proposed completion changed from July 30, 2027 to December 30, 2026
Hinkle substation β 10MW wind π¨ project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 17, 2020 to December 29, 2016
Hinkle substation β 10MW wind π¨ project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 17, 2020 to December 29, 2016
Hinkle substation β 10MW wind π¨ project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 17, 2020 to December 29, 2016
Alturas-Mile Hi transmission line β 1MW solar βοΈ project in Lake, OR (PacifiCorp). Proposed completion changed from May 26, 2019 to November 30, 2017
ARIDA 2 SOLAR FARM β 700MW battery + solar πβοΈ project in Clark, NV (CAISO). Proposed completion changed from December 29, 2027 to May 30, 2029
Deedsville 345 kV Substation β 292MW solar βοΈ project in Miami County, IN (MISO). Proposed completion changed from July 31, 2023 to July 31, 2026
115kV Strandahl sub β 255MW wind π¨ project in Williams County, ND (SPP). Proposed completion changed from October 29, 2026 to May 30, 2028
Substation 1363; 161kV Substation β 255MW gas π₯ project in Sarpy County, NE (SPP). Proposed completion changed from July 31, 2024 to June 16, 2025
Hickory Level - Yellow Dirt 230 kV Line β 250MW battery π project in Douglas County, GA (Southern Company). Proposed completion changed from April 14, 2029 to April 16, 2028
Goose Pond Road Substation 230 kV Bus, East Watkinsville - Goose Pond Road 230 kV Line β 250MW battery π project in Oglethorpe County, GA (Southern Company). Proposed completion changed from April 14, 2029 to April 16, 2028
Macomb to Ipava 138kV line β 200MW wind π¨ project in Mcdonough County, IL (MISO). Proposed completion changed from September 14, 2023 to September 14, 2026
Shockey 138kV β 200MW wind π¨ project in Logan County, IL (MISO). Proposed completion changed from October 30, 2023 to August 14, 2026
Eastman Primary - Hatch 230 kV Line β 199MW solar βοΈ project in Laurens County, GA (Southern Company). Proposed completion changed from April 14, 2029 to April 16, 2028
Ray Place Road - Washington #3 115 kV Line β 150MW solar βοΈ project in Taliaferro County, GA (Southern Company). Proposed completion changed from January 31, 2029 to January 16, 2028
Achord Road - Eastman Primary 230 kV Line β 150MW solar βοΈ project in Dodge County, GA (Southern Company). Proposed completion changed from August 14, 2028 to January 16, 2028
Hutsonville - Neoga 138 kV β 149MW solar βοΈ project in Cumberland County, IL (MISO). Proposed completion changed from July 31, 2023 to May 31, 2027
Bureau County 138 kV β 147MW wind π¨ project in Bureau County, IL (MISO). Proposed completion changed from July 31, 2022 to July 31, 2025
KENOWA - NELSON ROAD 345.0kV β 132MW solar βοΈ project in Montcalm County, MI (MISO). Proposed completion changed from October 31, 2023 to January 8, 2026
San Jose Rail Splitter 138KV (G515) β 100MW wind π¨ project in Tazewell County, IL (MISO). Proposed completion changed from August 31, 2024 to May 31, 2027
Eureka - Vestaburg 138kV Transmission Line (J1379 POI) β 100MW battery + solar πβοΈ project in Montcalm County, MI (MISO). Proposed completion changed from August 31, 2024 to June 6, 2027
Emery substation β 100MW battery π project in Emery, UT (PacifiCorp). Proposed completion changed from December 30, 2026 to June 29, 2027
Eastman Primary - Hatch 230 kV Line β 100MW battery π project in Laurens County, GA (Southern Company). Proposed completion changed from April 14, 2029 to April 16, 2028
ALTA VISTA SUNTOWER GENERATING STATION β 66MW battery + solar πβοΈ project in Los Angeles, CA (CAISO). Proposed completion changed from April 14, 2025 to December 10, 2027
Henry Solar β 20MW solar βοΈ project in Crawford County, PA (PJM). Proposed completion changed from July 30, 2027 to December 30, 2026
Hinkle substation β 10MW wind π¨ project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 17, 2020 to December 29, 2016
Hinkle substation β 10MW wind π¨ project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 17, 2020 to December 29, 2016
Hinkle substation β 10MW wind π¨ project in Umatilla, OR (PacifiCorp). Proposed completion changed from December 17, 2020 to December 29, 2016
Alturas-Mile Hi transmission line β 1MW solar βοΈ project in Lake, OR (PacifiCorp). Proposed completion changed from May 26, 2019 to November 30, 2017